Knowing what each good block leaving your plant costs you is the basis for setting prices, negotiating with large customers and deciding what to produce. The math is not hard, but it has traps: forgotten costs, dividing by the wrong units, or material losses nobody counts.

Start with the mix

The simplest way to get to the cost of a block is not to start with the block. Start with the mix: the concrete you prepare in one go, or the machine cycle, whatever your plant calls it. Almost every cost is easier to know per mix than per unit: how much material goes in, how long the crew works, how much energy the machine uses.

Once you have the cost of a mix, the cost of a block comes from dividing it by the units that mix produces. If mix sizes at your plant change from product to product, do the math for each product separately.

What goes into the cost

Make the full list before running numbers. The costs people forget most are the ones that are not paid every day.

  • Materials: what the mix uses, each with its quantity and the price you pay for it today, not six months ago.
  • Labor: what you pay the people who work on the mix, split by the time they spend on it.
  • Energy: electricity and fuel for the machines involved.
  • Other costs: maintenance, spare parts, water, moving product around the plant, and whatever share of overhead you want to charge to production.

Spread the monthly costs

Many costs are not paid per mix but per month: rent, security, the supervisor’s salary, parts bought every now and then. To charge them to each mix, add up the month’s amount and divide it by the number of mixes you made that month.

Watch this one: in a month when you produce little, each mix carries more fixed cost and the block gets more expensive. That is not a math error; it is what really happens when the plant runs below what it can do.

Divide by the good units

Here is the most common trap. A mix does not only produce blocks you can sell: some come out broken, others get damaged when they are moved, and others do not pass inspection. They all cost the same, but only the good ones bring in money.

That is why the mix cost is divided by the good units, not by the units produced. If you divide by the units produced, the cost comes out lower than it really is, and the difference eats into your margin without anyone noticing.

Do not forget the material you lose

Besides broken blocks, material gets lost: what spills, what is left over at the end of the shift, what sticks to the equipment. You paid for that material even though it is not in any block.

To include it, divide the material cost by the share you actually use. If a tenth is lost, divide by 0.9. If you do not know how much is lost, compare what you bought in a month with what your mix quantities say you should have used for what you produced.

An example with made-up numbers

The numbers in this example are made up and have no currency: they are only there so you can follow the math. Picture a mix with 220 in materials, 10% material waste, 60 in labor, 15 in energy and 5 in other costs, that yields 100 good blocks.

Material with waste is 220 divided by 0.9: about 244.44. The mix costs 244.44 plus 60, plus 15, plus 5: 324.44. Each good block costs 324.44 divided by 100: about 3.24. If you sell it for 4, you keep about 0.76 per block, almost 19% of the price.

From cost to price

With the cost per unit, you can look at the margin on every price you quote. Be careful how you measure it: margin on the selling price is not the same as markup on cost. In the example, 0.76 is almost 19% of the price and more than 23% of the cost. Pick one and stick with it.

Check special prices too. A volume discount or a price for a large customer can leave the margin at zero or below without anyone noticing, especially if the cost went up after the price was agreed.

Redo the math every month

The cost of a block is not a fixed number. It changes when a material goes up, when breakage increases or when a machine spends more time down. Do the math every month with that month’s real numbers and compare it with the previous one.

If the cost went up, the breakdown tells you where to look: pricier materials, more waste, fewer good units per mix, or more fixed costs spread over less production.

The numbers for this math, in Kembrio

In Kembrio, every production batch is logged with its product, its machine and the raw material it used, and the production dashboard shows the breakage rate and downtime. The purchasing module tracks purchase orders, suppliers and how spending evolves. That puts the numbers this calculation needs at hand.

Request a demo

See your plant running on Kembrio

We walk you through the system on a half-hour call, with products like yours. Leave us your details and we will get in touch.